长沙理工大学学报(自然科学版)
海底隧道大断面竖井快速成井技术研究
CSTR:
作者:
作者单位:

(1. 中国矿业大学 深地工程智能建造与健康运维全国重点实验室 ,江苏 徐州 221116;2. 中国中铁四局集团有限公司 ,安徽 合肥 230009)

作者简介:

通讯作者:

况联飞(1984—)(ORCID:0000-0002-3771-8521),男,副教授,主要从事深部地下工程方面的研究。E-mail:klfcumt@126.com

中图分类号:

U451;U455.8;U456.3

基金项目:

国家自然科学基金项目(52478377,51504245);中央高校基本科研业务费专项资金项目(2020ZDPYMS18)第一作者:覃业双(2001—),男,主要从事地下结构健康监测方面的研究。E-mail:ts24030210p31@cumt.edu.cn


Research on rapid construction technology for large -section shafts of subsea tunnels
Author:
Affiliation:

(1. State Key Laboratory of Intelligent Construction and Healthy Operation and Maintenance of Deep Underground Engineering , China University of Mining and Technology , Xuzhou 221116, China;2. China Railway No . 4 Engineering Group Co ., Ltd., Hefei 230009, China)

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    【目的】大断面竖井快速成井对海底隧道建设中的多头掘进施工及后续的通风运营均十分重要。为保证竖井建设的稳定性,改正传统竖井施工技术的单次掘砌段高与二次衬砌段高短、施工慢的缺点,以及实现大断面竖井的快速成井,本文以青岛市胶州湾第二海底隧道的黄岛端矩形断面竖井工程建设为背景,聚焦成井技术,并通过调整施工段高来提高施工效率,以达到快速成井的效果。【方法】本研究使用 PLAXIS 3D软件对竖井施工进行模拟,基于数值模拟结果和现场监测结果以及出于安全性与工程经验的考虑,对原施工段高进行优化,将单次掘砌段高由 1 m增加到 6 m、二次衬砌的施工段高调整为 10 m以上。【结果】在采用了优化后的施工工艺之后,整体工期缩短了 2个月。竖井围岩的位移收敛值随着施工深度的增加而增加,围岩的最大收敛值发生于掘进结束面底面,围岩位移水平方向的影响范围有限;当施工至不同岩层等级连接区域、节理发育带所在区域时,围岩强度较低、稳定性较差,导致该处位移收敛及波动幅度变大。锚杆受力、位移大小与围岩位移大小、施工深度呈现动态耦合现象,并存在锚杆安全冗余过高的现象。当采用 6 m的单次掘砌段高、10~20 m的二次衬砌施工段高时,模拟与监测所得的竖井水平位移收敛最大值分别为 10.1、16.4 mm,两者均小于 30 mm的预警值。【结论】在岩层稳定性良好的条件下,海底隧道竖井建设可通过优化单次掘砌支护段高与二次衬砌施工段高来提高施工速率,以达到快速成井的效果。同时,出于安全性、经济性等多方面的考虑,单次掘砌段高应控制在 6 m左右,二次衬砌施工段高应控制在 20 m以内,并可根据实际情况适当增大上部锚杆间距和相应减小下部锚杆间距,以保证围岩稳定性与施工经济性。

    Abstract:

    [Purposes ] The rapid construction of large -section shafts is crucial for multi -face tunneling operations and subsequent ventilation management in subsea tunnel construction.To ensure the stability of shaft construction,overcome the limitations of short excavation and support segment heights and slow construction in traditional shaft construction technologies,and achieve the rapid construction of large -section shafts,this paper took the Huangdao terminal shaft project of the Second Subsea Tunnel in Jiaozhou Bay,Qingdao City as the background,focused on the shaft construction technology,and improved the construction efficiency by adjusting the construction segment height to achieve rapid shaft construction.[Methods] This paper used PLAXIS 3D software to simulate the shaft construction.Based on the numerical simulation and field monitoring results,as well as considerations of safety and engineering experience,the original construction segment heights were optimized:The single excavation segment height was increased from 1 m to 6 m,and the secondary lining construction segment height was adjusted to more than 10 m.[Results] After adopting the optimized construction technology,the overall construction period is shortened by two months;the displacement convergence of the surrounding rock of the shaft increases with the increase of construction depth,and the maximum convergence value of the surrounding rock occurs at the bottom surface of the completed excavation section.The influence range of the horizontal displacement of the surrounding rock is limited.When the construction reaches the connection area of different rock stratum grades and the area where the joint development zone is located,the strength of the surrounding rock is low,and the stability is poor,resulting in a larger displacement convergence and fluctuation amplitude at these locations.The force and displacement of the anchor rods reach a dynamic coupling with the displacement of the surrounding rock and the construction depth,and there is a phenomenon of excessively high safety redundancy of the anchor rods.When a single excavation segment height of 6 m and a secondary lining construction segment height of 10-20 m are adopted,the maximum horizontal displacement convergence values of the shaft obtained by simulation and monitoring are 10.1 mm and 16.4 mm,respectively,both of which are less than the warning value of 30 mm.[Conclusions ] Under the condition of good rock stratum stability,the construction rate of subsea tunnel shafts can be improved by optimizing the single excavation and support segment height and the secondary lining construction segment height,so as to achieve the effect of rapid shaft construction.At the same time,considering safety,economy,and other factors,the single excavation and support segment height should be controlled at about 6 m,and the secondary lining construction segment height should be controlled within 20 m.In addition,the spacing of the upper anchor rods can be appropriately increased,and the spacing of the lower anchor rods can be correspondingly reduced according to the actual situation to ensure the stability of the surrounding rock and the construction economy.

    参考文献
    相似文献
    引证文献
引用本文

覃业双,况联飞,刘爱武,等.海底隧道大断面竖井快速成井技术研究[J].长沙理工大学学报(自然科学版),2026,23(3):172-183.
QIN Yeshuang, KUANG Lianfei, LIU Aiwu, et al. Research on rapid construction technology for large -section shafts of subsea tunnels[J]. Journal of Changsha University of Science & Technology (Natural Science),2026,23(3):172-183.

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2026-01-13
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2026-09-24
  • 出版日期:
文章二维码